Sg Perai pipe repair set for completion by 4pm today, says Chow

Repair works on track despite challenges faced by divers dealing with strong river currents, says Penang CM

2:33 PM MYT

 

BUTTERWORTH – Work to fix the clamps to repair the leak in the 1,350mm underwater pipe in Sg Perai here is expected to be completed by 4pm today, said Chief Minister Chow Kon Yeow.

This is despite the difficulties faced by the divers, who have to deal with the strong current at the bottom of the river.

Chow, who visited Sg Perai, said the divers have managed to clamp the upper part of the leaking pipe and work will continue to clamp the lower part.

“We are still on schedule and by 4pm today, we hope Plan A to fix the clamps can be completed,” he said, adding that once that is done, they hope to take further action to restore water to the affected areas as soon as possible through Plan B (the installation of new 600mm pipe channels).

Yesterday, the media quoted Chow as saying that a total of 120,000 water users in the Southwest area and some users in the Northeast would experience water supply disruptions for up to a week if Plan A fails.

The leak at the bottom of Sg Perai on Tuesday (January 23) was the third occurrence after two incidents of pipe leaks were reported in December last year and on January 12. 

Following several pipe leak incidents, the Penang government implemented a temporary replacement pipe installation method across Sg Perai, and installation works of the temporary pipe are expected to be completed on February 2, functioning for at least eight months while waiting for the new permanent replacement pipe project at the bottom of Sg Perai to be completed. – January 25, 2024

Topics

 

◉ Popular

MRCB unit, Saudi developer explore RM22.86bil Mecca transit-oriented project

Partnership with RUA AlHaram AlMakki to study mixed-use development within King Salman Gate, integrating transport, residential and hospitality components

DUN Melaka bubar berkuat kuasa esok

Dewan Undangan Negeri (DUN) Melaka dibubarkan secara rasmi berkuat kuasa esok selepas mendapat perkenan Yang Dipertua Negeri, Tun Mohd Ali Rustam, sekali gus memberi laluan kepada Pilihan Raya Negeri (PRN) ke-16 diadakan dalam tempoh 60 hari

TTDI hillside project floods again despite stop-work order

Residents’ fears materialise as mud and runoff spill into streets, prompting policy review on high-risk slope development

◉ Related